City to pave portions of Moraga Avenue and Highland Avenue April 11, 2016 through April 19th
Between April 11th and April 19th, the City of Piedmont will pave portions of Moraga and Highland Avenues between 9:00 a.m. and 4:00 p.m. each day. The project was timed to coincide as much as possible to the Piedmont Unified School District’s Spring Break. During the project one way traffic control will be in place at some times. Please use alternate routes if possible.
The project area will be Moraga Avenue between the eastern City limit and Pala Avenue as well as between Monticello Avenue and the western City limit. On Highland Avenue, the paving will take place between Sheridan Avenue and Highland Way.
The planned work schedule is:
- April 11th and 12th, grinding operations on Moraga Avenue.
- April 13th, 14th, and 15th grinding and paving operations on Highland Avenue.
- April 18th and 19th, paving operations on Moraga Avenue.
Work locations may be changed if conditions necessitate. Parking restrictions will be enforced in the work areas.
Residents with questions regarding the project should contact Public Works Supervisor Dave Frankel at (510) 207-2114.