SCHOOL BOARD CONSIDERATION IS ON MAY 13TH OF WHETHER TO PROCEED WITH CONSTRUCTION OF THE PERFORMING ARTS CENTER/NEW ALAN HARVEY THEATER OR WAIT.  FUNDING IS IN QUESTION.

 There has been some discussion of deferring for at least one year the second phase of the construction program — demolishing the 10s building and constructing a Performing Arts Center/New Alan Harvey Theater on the 10s site. The reasons for considering a delay include concerns over the sufficiency of contingency funds ($1.96 million), an interest in redesign to reduce overall cost, and, mostly recently, preserving the 10s building for increased social distancing.

Committee recommends moving ahead with the second phase and demolishing the 10s building.

A Measure H1 Facilities Program Update is linked here for your review.

READ the full staff report linked below:

PUSD 5132020

READ the agenda for the May 13 School Board meeting HERE.